PMP考試全真模擬題及答案(樣題)
申請(qǐng)免費(fèi)試用、咨詢電話:400-8352-114
PMP考試全真模擬題及答案(樣題)
1.Which of the following is true about accuracy and precision?
A. Precision is consistency and accuracy is correctness
B.Precision is correctness and accuracy is consistency
C.Precision and accuracy are same
D. Precision is used for measuring length and accuracy is used for time measurements Your
下列哪個(gè)關(guān)于正確度和精確度的說法是正確的?
A.精確度是說連續(xù)性;正確度是說是否符合事實(shí)
B.精確度是說是否符合事實(shí);正確度是說連續(xù)性
C.精確度和正確度是一樣的
D.精確度用來測(cè)量長(zhǎng)度;正確度用來測(cè)量你的時(shí)間
答案:A 參考:PMBOK2004 CH P154
2.Which process group is associated with schedule control, scope control, and cost control
A. Monitoring and Controlling
B. Planning
C. Executing
D. Closing
哪個(gè)過程組包括進(jìn)度控制,范圍控制和成本控制?
A.監(jiān)控項(xiàng)目
B.規(guī)劃
C.執(zhí)行
D.收尾
答案:A 參考:PMBOK2004 CH P58
3.In Probability and Impact Metrics which of the following statement is true?
A. For opportunities, the high risk (dark grey) zone offers greatest benefits
B. For opportunities, the low risk (medium grey) zone offers lowest risk and best benefits
C. for Risks the high risk (dark grey) zone offers greatest benefits
D. for Risks the low risk (medium grey) zone should be addressed first
關(guān)于概率和影響矩陣,下列哪個(gè)說法是正確的?
A.對(duì)機(jī)會(huì)而言,高風(fēng)險(xiǎn)(黑灰色)區(qū)域意味著代表最大的利益
B.對(duì)機(jī)會(huì)而言,低風(fēng)險(xiǎn)(中灰色)區(qū)域意味著最低的風(fēng)險(xiǎn)和最好的利益
C.對(duì)風(fēng)險(xiǎn)而言,高風(fēng)險(xiǎn)(黑灰色)區(qū)域意味著最大的利益
D.對(duì)風(fēng)險(xiǎn)而言,低風(fēng)險(xiǎn)(中灰色)區(qū)域應(yīng)該必須首先確定
答案:A 參考:PMBOK2004 CH P210
4.Zero defects practice or Do it first time is associated with which of the following?
A. Crosby
B. Juran
C. Deming
D. Shewhart
零缺陷或者事情一次作對(duì)和下列哪個(gè)有關(guān)?
A.克勞斯比
B.朱蘭
C.戴明
D.休哈特
答案:A
5.Which of the following would be the BEST description of project management plan?
A. It contains risk, cost, process improvement and other management plans.
B. It is one of the outputs of project management software.
C. it is milestone.
D. it is project scope statement.
下列哪個(gè)最好的描述了項(xiàng)目管理計(jì)劃?
A.包括風(fēng)險(xiǎn)、成本、過程改進(jìn)和其他管理計(jì)劃
B.是項(xiàng)目管理軟件的輸出之一
C.是里程碑
D.是項(xiàng)目范圍說明書
答案:A 解釋:用排除法,選一個(gè)相對(duì)合適的,注意選項(xiàng)B項(xiàng)目管理軟件不等于項(xiàng)目管理信息系統(tǒng)
6.Purchase order is the simplest example of _________ type of contract
A.T&M Contract
B. Fixed Price
C. Cost plus Incentive Fee
D. Cost plus Fixed Fee
采購(gòu)單是什么類型合同的例子?
A.時(shí)間材料合同
B.固定價(jià)格
C.成本加獎(jiǎng)勵(lì)費(fèi)用
D.成本加固定費(fèi)用
答案:B 參考:PMBOK2004 CH P230(仔細(xì)看能找到原文)
7.You are the project manager in East West Construction Company. After the completion of the structure you are visiting the site and checking whether the construction is as per the plan by taking the measurements. This is an example of
A. Risk Identification to prevent issues in the future
B. Active project management
C. Quality Assurance activity - Prevention
D. Quality Control Activity - Inspection
你是東西建筑公司的項(xiàng)目經(jīng)理。在完成建筑后,你到實(shí)施地點(diǎn)檢查是否建筑按照計(jì)劃進(jìn)行了測(cè)量。這是什么的例子?
A.風(fēng)險(xiǎn)識(shí)別用來防止未來出現(xiàn)的問題;
B.動(dòng)態(tài)項(xiàng)目管理
C.質(zhì)量保證活動(dòng)-預(yù)防
D.質(zhì)量控制活動(dòng)-檢查
答案:D 解釋:檢查作為工具出現(xiàn)在兩個(gè)過程,范圍核實(shí)和質(zhì)量控制
8.You are in charge of installing a Voice Response System for a major company. You are about to start preparing the estimates and the Sponsor informed you that the estimate should be as much close to reality as possible. Which of the following you will most likely to use for your estimation:
A.CPM
B.PERT
C.PDM
D. Monte Carlo Simulation
你在負(fù)責(zé)為某個(gè)大公司安裝聲音回傳系統(tǒng)。你開始準(zhǔn)備估算時(shí)出資人告訴你估算必須盡可能接近實(shí)際。你最可能使用下列哪個(gè)做你的估算?
A.CPM
B.PERT
C.PDM
D.蒙特卡羅模擬
答案:D 解釋:蒙特卡羅運(yùn)用統(tǒng)計(jì)學(xué)進(jìn)行模擬,相對(duì)而言比較貼近實(shí)際,也可以排除A和C都不是估算,選項(xiàng)B是缺乏經(jīng)驗(yàn)的時(shí)候使用的,最沒譜。
9.Create WBS is part which Knowledge Area?
A. Project Scope Management
B. Project Time Management
C. Project Integration Management
D. Project Cost Management
創(chuàng)建WBS是哪個(gè)知識(shí)領(lǐng)域的一部分
A.項(xiàng)目范圍管理
B.項(xiàng)目時(shí)間管理
C.項(xiàng)目整體管理
D.項(xiàng)目成本管理
答案:A
10.If the optimistic estimate for an activity is 18 and standard deviation is 3. If the Most likely estimate is 30, the chance the activity will be finished between 23 and 35 days is
A.95.44
B.68.26
C.99.73
D.99.999
如果某個(gè)活動(dòng)的樂觀估計(jì)是18天,標(biāo)準(zhǔn)差是3。如果最可能估計(jì)是30天,這個(gè)活動(dòng)在23天到35天之間完成的概率是?
A.95.44
B.68.26
C.99.73
D.99.999
答案:A 解釋:這個(gè)活動(dòng)的最悲觀估計(jì) X,(X-18)/6=3;所以最悲觀是36;平均估算值=(54+120)/6=29;23到35,剛好左右各兩個(gè)標(biāo)準(zhǔn)差,概率為95.44%
相關(guān)推薦:
2011年P(guān)MP模擬習(xí)題匯總(附參考答案)
PMP考試模擬試題
- 1安全工程師生產(chǎn)管理復(fù)習(xí)要點(diǎn):風(fēng)險(xiǎn)
- 22015年招標(biāo)師《專業(yè)實(shí)務(wù)》輔導(dǎo):貨物評(píng)標(biāo)的詳細(xì)評(píng)審要點(diǎn)
- 3"金九銀十"亦未能改變樓市低迷 兇猛價(jià)格戰(zhàn)或?qū)砼R
- 42015年咨詢工程師《工程咨詢概論》每日一練(9.6)
- 5一級(jí)建造師項(xiàng)目管理復(fù)習(xí)要點(diǎn):建設(shè)單位
- 6某園林景觀工程施工組織設(shè)計(jì)42p
- 72015安全工程師考試預(yù)習(xí)知識(shí)點(diǎn):從業(yè)人員的監(jiān)督
- 8園林景觀施工組織設(shè)計(jì)方案36p
- 9試驗(yàn)室安全用電管理制度
- 102015招標(biāo)師《項(xiàng)目管理與招標(biāo)采購(gòu)》:國(guó)際貿(mào)易適用的慣例
- 11不屬于風(fēng)險(xiǎn)事件發(fā)生前風(fēng)險(xiǎn)管理目標(biāo)的是哪個(gè)
- 122015年二級(jí)建造師《法規(guī)及相關(guān)知識(shí)》每日一練(12.13)
- 13南方電網(wǎng)千伏輸變電工程造價(jià)分析通過專家驗(yàn)收
- 14十臨邊設(shè)防護(hù)欄桿還用封拉立網(wǎng)嗎
- 152012一級(jí)建造師《項(xiàng)目管理》:施工質(zhì)量事故處理的基本方法
- 162015年造價(jià)工程師考試《計(jì)價(jià)控制》第三章講義(21)
- 17建設(shè)工程目標(biāo)控制的措施典型題解(二)
- 182015.9.2咨詢工程師每日一練免費(fèi)在線測(cè)試
- 192015年咨詢工程師每日一練免費(fèi)在線測(cè)試(2015.5.9)
- 20造價(jià)工程師案例分析復(fù)習(xí)資料——流動(dòng)資金估算
- 212015一級(jí)建造師《鐵路工程》復(fù)習(xí)指南(18)
- 22造價(jià)工程師工程計(jì)價(jià)復(fù)習(xí)要點(diǎn):定額計(jì)算
- 23安全工程師考試《安全生產(chǎn)法及相關(guān)法律知識(shí)》模擬題(7)
- 24天津公布2015安全工程師報(bào)名時(shí)間:6月15日至6月29日
- 25觀察煙霧確診攪拌車癥狀
- 26馬鞍山市住建委開展農(nóng)村清潔工程危房改造和村莊整治工作督查
- 27[江門]2008年度注冊(cè)安全工程師執(zhí)業(yè)資格考試5月12-16日?qǐng)?bào)名確認(rèn)
- 282015年監(jiān)理工程師《基本理論與相關(guān)法規(guī)》模擬題(6)
- 292012一級(jí)建造師《公路工程》:施工組織設(shè)計(jì)的編寫
- 30復(fù)合式襯砌鐵路隧道工程實(shí)施性施工組織設(shè)計(jì)(噴錨支護(hù) 臺(tái)階法)
成都公司:成都市成華區(qū)建設(shè)南路160號(hào)1層9號(hào)
重慶公司:重慶市江北區(qū)紅旗河溝華創(chuàng)商務(wù)大廈18樓