當(dāng)前位置:工程項目OA系統(tǒng) > 建筑OA系統(tǒng) > 軟件項目管理工具
PMP認(rèn)證考試練習(xí)題(四)(中英文)
1. In order to approve a project, management using simple, as well as complex, sophisticated tools to determine how the project fits into it’s strategic plan. When the project selection includes an in-depth analysis, using complex, sophisticated tools, is os considered to be part of what project phase?
Implementation
Termination
Conceptual
Operational
None of the above
為了批準(zhǔn)項目,管理層使用簡單的,但同復(fù)雜技術(shù)的一樣好的,久經(jīng)考驗的工具測量項目如何滿足它的策略計劃. 當(dāng)項目選擇一個包含有深層次分析的,復(fù)雜的,久經(jīng)考驗的工具時,它發(fā)生在項目的那一個階段?
執(zhí)行
終止
概念上
運做
上述都不是
2. What is the most accurate method of obtaining project information that can reduce the amount of risk?
Observations on the current project
Determining the risk by using painstorming techniques
The use of historical data from previous projects that were similar in nature
Sensitivity analysis
Delphi technique
那一個是獲得項目信息以降低項目風(fēng)險總量的最精確的方法?
觀察當(dāng)前項目
應(yīng)用集體討論方法決定風(fēng)險
使用以前類似項目的歷史數(shù)據(jù)
敏感分析
Delphi 技術(shù)
3. Contained within the first step of a five step process to determine the risk analysis of the project’s risk events, a process of ________ is performed to see if the risk should be included or excluded as part of the project scope.
Determining the probability
Contingency effort
Assessing the consequences and severity
Screening
在5步過程的第一步內(nèi),下列那一個過程是決定項目風(fēng)險事件的風(fēng)險分析,它被用于判斷風(fēng)險是否應(yīng)當(dāng)作為項目范圍的一部分包括在內(nèi)或不在內(nèi).
可能性決定
應(yīng)急措施
評估因果關(guān)系和嚴(yán)重程度
放映
4. A project of 2 million has an adverse event that has the probability of 50% of occurrence and a potential loss of $20,000. This represents an expected negative value of:
$100,000
$1,000
$100
$10,000
一個2百萬的項目隱含有一個不利的影響,它發(fā)生的可能性是50%,潛在損失是2萬. 它的預(yù)期負(fù)值是多少:
$100,000
$1,000
$100
$10,000
5. The assigned values of risk for a project is best accomplished through a structured methodology that ensures all project elements are evaluated. The project tool that is best suited for the structured analysis of the project risk is the:
Contract
Specification
Statement of work
Work peakdown structure
Network programming diagram
對一個項目,假定的風(fēng)險值最好是通過一個結(jié)構(gòu)的方法論來完成以便所有項目的因素都被評估. 用于項目風(fēng)險的結(jié)構(gòu)分析的最合適的工具是:
合同
規(guī)范
工作描述
工作分解結(jié)構(gòu)
網(wǎng)絡(luò)規(guī)劃圖
6. The total amount of risk that is calculated for a project is found by:
Multiplying the sum of each the risks times the amount at stake
Calculating the cumulative sum of the probability for each risk and multiplying this value times the consequence of occurrence of the risk events
Cannot be calculated since all risks are not known
The amount of project reserves available
通過那一種手段來計算項目風(fēng)險的總量:
每個風(fēng)險的總和乘以風(fēng)險的價值量
計算每個風(fēng)險的可能性累計總和同時轉(zhuǎn)換成價值乘以風(fēng)險事件發(fā)生的頻率
由于所有風(fēng)險不確定不能計算
項目的可用的儲備金
7. Bo calls his project team to quantify and assess the risks of their project. The benefits the team will gain from this exercise include all but which of the following?
Thoroughly understand the project, the associated risks and the impact of risk on all parts of the project
Develop risk mitigation strategies for dealing with issues identified
Ensure all identified risk issues are incorporated into project planning
Identify alternatives which may exist
玻叫他們的項目組把項目的風(fēng)險量化和評估. 哪一相不是項目組從這一活動中得到的?
徹底地了解項目,相關(guān)的風(fēng)險和項目所有部分的風(fēng)險的影響
進(jìn)一步發(fā)展緩解風(fēng)險策略以處理已經(jīng)確認(rèn)的問題
保證所有已經(jīng)確認(rèn)的風(fēng)險都被統(tǒng)一的考慮在項目的計劃中
確認(rèn)那一個可能存在的選擇方案
- 1學(xué)校工程施工現(xiàn)場平面布置圖
- 2安全工程師考試《安全生產(chǎn)管理》第一講講義精選(1)
- 32015年咨詢工程師《工程咨詢概論》每日一練9.18
- 42015年咨詢工程師每日一練免費在線測試(2015.5.29)
- 5《宏觀經(jīng)濟(jì)政策與發(fā)展規(guī)劃》知識點:產(chǎn)業(yè)結(jié)構(gòu)調(diào)整的目標(biāo)
- 62015年招標(biāo)師《專業(yè)實務(wù)》輔導(dǎo):工程建設(shè)項目設(shè)計管理特征
- 7腳手架的拆卸必須符合的安全要求
- 82015年湛江市安全工程師考試報名截止時間為6月21日
- 9資金時間價值及習(xí)題
- 102015年咨詢工程師《工程項目組織與管理》每日一練匯總2.25-3.3
- 11平板機安全要求
- 122015造價員《土建工程》基礎(chǔ)知識點:強夯工程
- 13項目材料、機械設(shè)備、工程技術(shù)人員的管理責(zé)任內(nèi)容
- 14造價工程師考試輔導(dǎo):成本與費用的估算(1)
- 152015招標(biāo)師考試項目管理考點:貨物生產(chǎn)供應(yīng)鏈
- 162013年四川二級建造師變更注冊申請表
- 1724米跨雙線簡支箱型梁制造施工工法
- 182015招標(biāo)師考試項目管理考點:招標(biāo)采購項目計劃的編制
- 19武黃城際鐵路施工有條不紊 黃石北站八月份竣工
- 202011年P(guān)MP考試試題分布更新通知
- 21國家能源局:禁建年產(chǎn)20億方以下煤制氣項目
- 222015安全工程師《安全生產(chǎn)法及法律知識》鞏固練習(xí)(2)
- 232015年咨詢工程師:投資估算的范圍與內(nèi)容
- 24大廈工程施工現(xiàn)場平面布置圖(基礎(chǔ)、結(jié)構(gòu)、裝修)
- 252015年造價工程師考試輔導(dǎo):工程壽命周期成本
- 262015年咨詢工程師《工程咨詢概論》考試模擬試題(8)
- 27成綿樂客專鋪軌完成60% 預(yù)計年底通車
- 282015年富陽市造價工程師考試報名時間為6月16日至30日
- 292015年咨詢工程師《組織與管理》每日一練(4.19)
- 30《招標(biāo)采購法律法規(guī)與政策》第三章:對備選方案的處理辦法
成都公司:成都市成華區(qū)建設(shè)南路160號1層9號
重慶公司:重慶市江北區(qū)紅旗河溝華創(chuàng)商務(wù)大廈18樓