QUEST Many companies self insure against some risk.  Problems which can arise from self-insurance include: 
A failure to reserve funds to handle worst case scenarios (low probability events) resulting in severe financial damage to the company 
B stiff competition from insurance companies 
C confusion of business risks with insurable risks. 
D A and C 
E All of the above. 
參考答案:D

QUEST Sensitivity analysis can be used in risk analysis to: 
A Substitute for uncertainty analysis in risk quantification 
B estimate the level of risk aversion adopted by management 
C estimate the effect of change of one project variable on the overall project 
D A and B 
E All of the above. 
參考答案:C

QUEST Risk event probability is defined as: 
A the total number of possible events divided into the expectations or frequency of the risk event 
B the number of times the risk event may occur 
C the fraction of the total project tasks which may be affected by the risk event 
D the total number of possible events divided into the consequences of the risk event. 
E A and B 
參考答案:A

QUEST In Project Risk Management, Risk Response may include actions to: 
A reduce the probability of risk events 
B change the scope, budget, schedule or quality specifications of the project 
C reduce the consequences or severity of impacts of a potential risk event 
D A and C 
E All of the above. 
參考答案:E

QUEST Total Project Risk: 
A should not be calculated for small projects 
B is the probability of each project risk event times the sum of the consequences of individual project risk events which could occur during the project. 
C Is the cumulative sum of the probability of each individual project risk event times the consequences of occurrence of that risk event. 
D A and B 
E A and C 
參考答案:C

相關(guān)試題:

2010年P(guān)MP美國項(xiàng)目管理考試習(xí)題及答案16

試題推薦:

2010年P(guān)MP美國項(xiàng)目管理認(rèn)定考試全真模擬試題精選1

2010年P(guān)MP美國項(xiàng)目管理認(rèn)定考試全真模擬試題精選2

2010年P(guān)MP美國項(xiàng)目管理認(rèn)定考試全真模擬試題精選3

發(fā)布:2007-03-02 10:53    編輯:泛普軟件 · xiaona    [打印此頁]    [關(guān)閉]
相關(guān)文章:

泛普軟件項(xiàng)目管理工具其他應(yīng)用

項(xiàng)目管理工具 禪道項(xiàng)目管理軟件 夢(mèng)龍項(xiàng)目管理軟件 微軟項(xiàng)目管理軟件 裝飾管理系統(tǒng) 裝修預(yù)算軟件 項(xiàng)目計(jì)劃軟件 項(xiàng)目進(jìn)度管理軟件 軟件項(xiàng)目管理工具 材料管理軟件 工程項(xiàng)目管理軟件系統(tǒng) 項(xiàng)目管理系統(tǒng) 施工管理軟件 建筑工程項(xiàng)目管理軟件 工程管理軟件