2010年PMP美國項目管理考試習題及答案四十六

申請免費試用、咨詢電話:400-8352-114

QUEST Which of the following is referred to as payback period: 
A the number of periods required to recover the initial investment 
B the rate of return on  the investment 
C the number of periods required to bring project cost back to the original budget, based on current performance 
D loan payment schedule 
E None of the above 
參考答案:A

QUEST Which of the following is referred to as sunk cost: 
A management reserve 
B contingency fund 
C cost budgeted for construction under water 
D expended funds over which there is no further control 
E forecasted budget over-runs 
參考答案:D

QUEST The future value of an annual income flow of $1000 for 2 years at 10% is: 
A ¥2,200 
B ¥2,280 
C ¥2,300 
D ¥2,310 
E None of the above 
參考答案:D

QUEST The net present value of $110 one year from now at 10% is: 
A ¥100 
B ¥120 
C ¥121 
D $100 less taxes 
E $100 less taxes and interest 
參考答案:A

QUEST Which of the following depreciation methods provides for accelerated depreciation of an asset: 
A Double declining balance. 
B Straight line. 
C Exponential depreciation 
D Double sum of the years digits 
E Double increasing balance 
參考答案:A

相關試題:

2010年PMP美國項目管理考試習題及答案四十五

試題推薦:

2010年PMP美國項目管理認定考試全真模擬試題精選1

2010年PMP美國項目管理認定考試全真模擬試題精選2

2010年PMP美國項目管理認定考試全真模擬試題精選3

發(fā)布:2007-03-02 10:54    編輯:泛普軟件 · xiaona    [打印此頁]    [關閉]
相關文章:

泛普軟件項目管理工具其他應用

項目管理工具 禪道項目管理軟件 夢龍項目管理軟件 微軟項目管理軟件 裝飾管理系統(tǒng) 裝修預算軟件 項目計劃軟件 項目進度管理軟件 軟件項目管理工具 材料管理軟件 工程項目管理軟件系統(tǒng) 項目管理系統(tǒng) 施工管理軟件 建筑工程項目管理軟件 工程管理軟件