QUEST The first step in building a PERT/CPM network is to: 
A Create a flow chart 
B Determine the critical path 
C Show task relationships 
D Create a work breakdown structure 
E None of the above. 
參考答案:D

QUEST The critical path in a schedule network is the path that: 
A Takes the longest time to complete 
B Must be done before any other tasks 
C Allows some flexibility in scheduling a start time. 
D Is not affected by schedule slippage 
E All of the above. 
參考答案:A

QUEST Assume that you have a network where an activity on the critical path can be crashed by two weeks.  If the activity is actually crashed by two weeks, then: 
A The project's schedule will be reduced by 2 weeks. 
B The available slack on the noncritical paths will increase. 
C A new critical path may appear after the crash. 
D All of the above. 
E A and B only. 
參考答案:C

QUEST Your team has prepared a CPM schedule for your review.  You notice that one node has six inputs (including two dummy activities) and four outputs (which include one dummy activity).  Select the correct statement from the following: 
A This is a valid representation if the logic is correct. 
B This is invalid because a node can have a maximum of one dummy input representation if the logic is correct. 
C This is invalid because nodes cannot have both dummy inputs and dummy outputs. 
D This is a invalid because the number of outputs must equal the number of inputs. 
E This is invalid because a maximum of two inputs and two outputs are allowed using the critical path method. 
參考答案:A

QUEST During project execution, the customer authorizes and funds a scope change which requires a major change in the schedule.  The baseline schedule: 
A Now becomes the new schedule, including the changes, and the original baseline is disregarded. 
B Is still the original baseline but annotated to reflect that a change has taken place. 
C Is amended to reflect the scope change, but the original baseline is still maintained for post-project review. 
D Is meaningless since every schedule update changes the baseline (i.e., a rubber baseline.) 
E Is the same since baseline schedules cannot change once the development phase is completed. 
參考答案:C

相關(guān)試題:

2010年P(guān)MP美國項目管理考試習(xí)題及答案二十九

試題推薦:

2010年P(guān)MP美國項目管理認定考試全真模擬試題精選1

2010年P(guān)MP美國項目管理認定考試全真模擬試題精選2

2010年P(guān)MP美國項目管理認定考試全真模擬試題精選3

發(fā)布:2007-03-02 10:55    編輯:泛普軟件 · xiaona    [打印此頁]    [關(guān)閉]
相關(guān)文章:

泛普軟件項目管理工具其他應(yīng)用

項目管理工具 禪道項目管理軟件 夢龍項目管理軟件 微軟項目管理軟件 裝飾管理系統(tǒng) 裝修預(yù)算軟件 項目計劃軟件 項目進度管理軟件 軟件項目管理工具 材料管理軟件 工程項目管理軟件系統(tǒng) 項目管理系統(tǒng) 施工管理軟件 建筑工程項目管理軟件 工程管理軟件