當(dāng)前位置:工程項(xiàng)目OA系統(tǒng) > 建筑OA系統(tǒng) > 軟件項(xiàng)目管理工具
礪志PMP模擬題每周精選3
申請(qǐng)免費(fèi)試用、咨詢(xún)電話(huà):400-8352-114
Qustions 1:The change control system includes--
a. Procedures to define how documents may be changed
b. Specific change requests expected on the project and plans to respond to each one
c. Performance reports that forecast project changes
d. A description of the functional and physical characteristics of an item or system
Qustions 3:
Typically, change control systems include automatic approval of certain types of changes. An example of such a change is one that is--
a. Suggested by the project sponsor
b. The result of an emergency
c. Suggested by the customer
d. Made mandatory by a new regulation
Qustions 5:
Rolling wave planning provides information on the work to be done--
a. Throughout all phases of the project
b. For successful completion of the current phases of the project
c. For successful completion of the current phase and subsequent phases of the project
d. In the next phase of the project
Qustions 2:
According to Herzberg’s motivator-hygiene Theory of Motivation, if achievement, recognition, responsibility, advancement or promotion, and positive supervisor attitude are not present, employees will--
a. Become alienated with the organization and leave
b. Lack motivation but will not be dissatisfied with their work
c. Lack motivation and become dissatisfied with their work
d. Become dissatisfied only if they do not receive salary increases
Qustions 4:
Problem solving, which is an important activity on projects, consists of --
a. Influencing the organizations to get things done
b. Defining problems and making decisions
c. Conferring with others to reach a dicision
d. Producing key results expected by stakeholders
Qustions 6:
Configuration management describes procedures to apply technical and administrative direction. Which of the following tasks is not performed in configuration management --
a. Identifying functional and physical characteristics of an item or system
b. Controlling changes to characteristics
c. Performing an audit to verifiy conformance to requierments
d. Allowing automatic approval of changes
- 1安全工程師備考知識(shí)輔導(dǎo):煤礦生產(chǎn)中的安全管理2
- 2項(xiàng)目進(jìn)度管理用哪些管理工具比較好?
- 32015年監(jiān)理工程師考試?yán)碚撆c法規(guī)練習(xí)題(16)
- 42015年二級(jí)建造師:門(mén)窗工程施工技術(shù)要求
- 5“建在巖溶上的地鐵”9號(hào)線(xiàn)全速開(kāi)挖
- 6一級(jí)建造師管理與實(shí)務(wù)復(fù)習(xí)要點(diǎn):盾構(gòu)問(wèn)題
- 7經(jīng)濟(jì)政策與發(fā)展規(guī)劃考點(diǎn):投資變動(dòng)的宏觀效應(yīng)
- 8安全工程師安全生產(chǎn)法復(fù)習(xí)資料——責(zé)任者
- 9混凝土輸送泵液壓油的更換
- 10工程項(xiàng)目組織與管理知識(shí)點(diǎn):工程項(xiàng)目范圍確認(rèn)
- 11對(duì)組織者或者積極參加者
- 12鋼筋混凝土預(yù)制沉井施工
- 13北京地區(qū)06年注冊(cè)安全工程師執(zhí)業(yè)資格2568人參考
- 142008年安全工程師考試《安全生產(chǎn)技術(shù)》習(xí)題七
- 15一級(jí)建造師市政公用工程管理與實(shí)務(wù):防水卷材
- 162015監(jiān)理工程師考試《建設(shè)工程合同管理》測(cè)試題(九)
- 17三合一自粘防水卷材的施工工藝
- 18二級(jí)建造師法規(guī)知識(shí)點(diǎn):建設(shè)工程賠償損失的范圍與特征
- 19全新造價(jià)通平臺(tái)開(kāi)啟工程造價(jià)信息化第五代應(yīng)用
- 20造價(jià)工程師建設(shè)工程計(jì)價(jià)復(fù)習(xí)資料——國(guó)內(nèi)競(jìng)爭(zhēng)性招標(biāo)
- 21招標(biāo)師職業(yè)水平考試:招標(biāo)采購(gòu)專(zhuān)業(yè)實(shí)務(wù)第八章練習(xí)題(匯總)
- 22湖北:今后3年將建普通公路4.5萬(wàn)公里
- 23“四口”防護(hù)措施
- 24某商務(wù)大廈景觀水景噴泉方案
- 25杭州某食品車(chē)間項(xiàng)目施工平面布置圖
- 26一級(jí)建造師《工程經(jīng)濟(jì)》知識(shí)點(diǎn)整理(9)
- 272015年白銀造價(jià)工程師報(bào)名入口
- 282015造價(jià)員復(fù)習(xí)資料:做好現(xiàn)場(chǎng)的調(diào)查工作
- 292015年監(jiān)理工程師考試?yán)碚撆c法規(guī)練習(xí)題(69)
- 30《工程項(xiàng)目組織與管理》:工程項(xiàng)目合同的特點(diǎn)
成都公司:成都市成華區(qū)建設(shè)南路160號(hào)1層9號(hào)
重慶公司:重慶市江北區(qū)紅旗河溝華創(chuàng)商務(wù)大廈18樓