項(xiàng)目職業(yè)道德練習(xí)題及答案(14)

申請(qǐng)免費(fèi)試用、咨詢電話:400-8352-114

項(xiàng)目職業(yè)道德練習(xí)題及答案(14)

11. Each of the following describes the use of an ethical approach except:
a. Attempting to understand the religious and cultural sensitivities of the country in which you have been assigned.
b. Ensuring that personal interest does not interfere with your decision making process.
c. Accepting gifts in exchange for favoring one contractor over another
d. Maintaining confidentiality of sensitive information obtained during the project life cycle.
12. To maintain the customer's schedule, massive overtime will be required between Christmas and New Years. Many of your team members have put in for vacation during this time. You should:
a. Let the schedule slip and inform the customer
b. First give the employees the choice of working overtime
c. Make the employees cancel their vacation plans and work overtime
d. Hire temporary employees for the overtime
13. Which of the following situations describes a violation of the PMP?Professional Code of Conduct?
a. Accepting a gift that is within the customary guidelines of the country or province you are currently working in.
b. Use of confidential information to advance your position or influence a critical decision.
c. Complying with laws and regulations of the state or province in which project management services are provided
d. Disclosing information to a customer about a situation that may have an appearance of impropriety.
14. In order to balance the needs of the many stakeholders involved in your project the most desirable method to achieve resolution of conflicts would be:
a. Compromise
b. Forcing
c. Controlling
d. Confrontation
15. You receive a contract to perform testing for an external client. After contract award, the customer provides you with the test matrix to use for your 16 tests. The vice president for engineering says that the customer's test matrix is wrong, and she will use a different test matrix, which should give better results. This is a violation to the SOW. Suppose your sponsor is also the vice president for engineering. You should:
a. Use the customer's test matrix
b. Use the engineering test matrix without telling the customer
c. Use the engineering test matrix and inform the customer
d. Tell your sponsor that you want to set up a meeting with the customer to resolve the conflict
16. In order for the project manager to fully and effectively understand a stake holder's personal concerns or grievances it may necessary to:
a. Ask for a written description of the problem and submit it through the project office
b. Schedule a project review session with the entire project team
c. Attempt to empathize with the stakeholder
d. Involve the project sponsor as an arbitrator
17. As the leader of a project team, the project manager may be required to assess the competencies of his or her team members. Occasionally, some weaknesses or areas for improvement will be identified. The project manager should:
a. Remove any team members who have demonstrated weaknesses in critical knowledge areas
b. Communicate those weaknesses and establish a performance improvement program
c. Hire additional resources to compensate for weak areas
d. Wait for the team members to fail in an assignment to justify termination.
18. You have just changed jobs and discovered that your new employer routinely violates OSHA/EPA and affirmative action requirements on projects. You should:
a. Do nothing; it's not your problem
b. Start by asking management if they are aware that regulations are being violated
c. Talk to the corporate legal department
d. Inform the appropriate government agencies about the violations
19. The project manager must be an effective communicator to ensure that project stakeholders receive and understand project related information and status. Prior to delivering information to the stakeholders the project manager should attempt to:
a. Research and understand the region of experience of the stakeholder before transmitting information
b. Identify only those stakeholders that have a the same background experience as the project manager
c. Filter the information to remove any details
d. Restrict information to specific technical details
20. As part of your project plan you must develop an effective method of communication for your multinational team of stakeholders. You have several choices of media available. The appropriate action to take in the development of the communication plans would be to:
a. Discuss the available options with the stakeholders and obtain their input
b. Use the standard media that has been in effect for your previous projects
c. Use multiple forms of media to ensure that everyone receives the information
d. Obtain additional funding from the project sponsor and develop a project specific communications infrastructure.
21. One of your employees is up for promotion. If the promotion is granted, the employee will be reassigned elsewhere causing a problem for you on your project. You can delay the promotion until your project is completed. You should:
a. Support the promotion but work with the employee and the employee's new management to develop a good transition plan
b. Ask the employee to refuse the promotion until your project is completed.
c. Arrange to delay the promotion until the project is completed
d. Tell the employee that it is his responsibility to find a suitable replacement so that the project will not suffer.
22. The integrity of the project manager is often challenged by stakeholders who attempt to use personal power or influence to change the scope of an agreed upon deliverable. In these situations the project manager's most appropriate response would be:
a. Refer the stakeholder to the process for change documented in the approved contract.
b. Agree to the change because customer satisfaction is the goal regardless of cost.
c. Contact the legal department and suspend all further project work
d. Determine the risks and rewards for implementing the change before taking any action.
23. During project implementation the client interprets a clause in the contract to mean the he is entitled to a substantial refund for work recently completed. You review the clause and disagree with the client's conclusion. As the project manager which of the following actions should be taken
a. Disregard the customer's conclusion and continue to process invoices
b. Document the dispute and refer to the provisions of the contract that address interpretations and disputes
c. Advise the customer that ambiguous information in contracts is always interpreted in favor of the contractor
d. Immediately correct the clause to remove any possible misinterpretation by the customer
24. Your executives, in appreciation for the success of your project, have given you a $10,000 bonus to be disbursed among your five-team members. One of the five, who is a substandard worker and accomplished very little on your project, is in your car pool. You should:
a. Provide everyone with an equal share
b. Provide everyone a share based upon their performance
c. Ask the workers to decide among themselves how the bonus should be subdivided
d. Ask the sponsor to make the decision
25. Before reporting a perceived violation of an established rule or policy the project manager should
a. Determine the risks associated with the violation
b. Ensure there is a reasonably clear and factual basis for reporting the violation
c. Ignore the violation until it actually affects the project results
d. Convene a committee to review the violation and determine the appropriate response
26. Project Managers can contribute to their organization's knowledge base and to the profession of project management most effectively by:
a. Developing and implementing a project review and lessons learned process
b. Establishing strict guidelines for protecting intellectual property
c. Promote the use of ad hoc project management
d. Ensuring that all project plans are developed before the project team is formed
27. You have been assigned two concurrent projects. Because of the nature of the projects, you have a conflict of interest. You should:
a. Do the best you can and tell no one
b. Ask to be removed from one of the projects
c. Ask to be removed from both of the projects
d. Inform your sponsor and ask for his advice
28. You receive a contract to perform testing for an external client. After contract award, the customer provides you with the test matrix to use for your 16 tests. The vice president for engineering says that the customer's test matrix is wrong, and she will use a different test matrix, which should give better results. This is a violation to the SOW. You should:
a. Use the customer's test matrix
b. Use the engineering test matrix without telling the customer
c. Use the engineering test matrix and discuss the reasons with the customer
d. Ask your sponsor for clarification, assuming that the vice president is not your sponsor
29. An effective method for improving an organization's project management knowledge base is through:
a. Coaching and mentoring
b. Referent power
c. A weak Matrix organizational structure
d. Fast Tracking

Answer Key

11=c
12=b
13=b
14=d
15=d
16=c
17=b
18=b
19=a
20=a
21=a
22=a
23=b
24=c
25=b
26=a
27=d
28=d
29=a