項(xiàng)目管理師考前模擬試題(一)及參考答案
1. A narrative description of products or services to be supplied under contract is called:
A. The project plan.
B. A statement of work.
C. An exception report.
D. A Pareto analysis.
2. An example of scope verification is:
A. Reviewing the performance of an installed software module.
B. Managing changes to the project schedule.
C. Decomposing the WBS to a work package level.
D. Performing a benefit/cost analysis to determine if we should proceed with the pro
3. Which of the following is not an example of a source of scope change?
A. A variation in government regulations.
B. Failure to include a required feature in the design of a telecommunication system.
C. A need to engage in bottom-up cost estimating.
D. Introducing technology that was not available when scope was originally defined.
4. The subdivision of major project deliverables, as identified in the scope statement, into smaller, more manageable components is called:
A. Parametric estimation.
B. Scope definition.
C. Feasibility analysis.
D. Benefit-cost analysis.
5. The process of establishing clear and achievable objectives, measuring their achievement, and adjusting performance in accordance with the results of the measurement is called:
A. Strategic planning.
B. Alternative objectives inventory.
C. Management by objectives.
D. Contingency planning.
6. Configuration management is:
A. Used to ensure that the description of the project product is correct and complete.
B. The creation of the work breakdown structure.
C. The set of procedures developed to assure that project design criteria are met.
D. A mechanism to track budget and schedule variances.
7. A fundamental tenet of modern quality management holds that quality is most likely to be achieved by:
A. Planning it into the project.
B. Developing careful mechanisms to inspect for quality.
C. Striving to do the best job possible.
D. Conducting quality circle activities.
8. Your most recent project status report contains the following information: BCWP = 3,000, ACWP = 3,500, and BCWS = 4,000. The schedule variance is:
A. + 1,000.
B. + 500.
C. - 500.
D. - 1,000.
9. Learning curve theory emphasizes that in producing many goods:
A. Cost decreases as production rates increase.
B. Average unit cost decreases as more units are produced.
C. Materials become cheaper when they are purchased in bulk.
D. Laborers become more productive because of technological advances.
10. Rearranging resources so that constant resource levels are maintained is called:
A. Floating.
B. Leveling.
C. Restructuring.
D. Crashing. 11. The _________ is a time-phased budget that will be used to measure and monitor cost performance in the project.
A. Work breakdown structure
B. Project schedule
C. Cost baseline
D. Cost budget
12. To transfer most of the cost risk to the contractor, the client may use a ___________ contract.
A. Cost plus award
B. Cost plus incentive fee
C. Cost plus fixed fee
D. Fixed price
13. An appropriate sequence for risk management activities is:
A. Risk identification, risk quantification, and risk response development and control.
B. Risk identification, risk assessment, and risk planning.
C. Risk identification, risk mitigation, and risk management.
D. Risk identification, risk elimination, and risk mitigation.
14. Theory X holds that:
A. Quality improvements lie in the hands of quality circles.
B. Profits are tied to meeting schedule deadlines.
C. Absenteeism is tied to poor working conditions.
D. Workers are inherently unmotivated and need strong guidance.
15. All of the following are characteristics of parametric estimating except:
A. Historical information.
B. Quantifiable.
C. Scalable.
D. Activity lists.
16. Inputs to cost budgeting include all of the following except:
A. Cost baseline
B. Cost estimate
C. Work breakdown structure
D. Project schedule
17. Inputs used during scope planning include all of the following except:
A. Constraints.
B. Project charter.
C. Budget/cost analysis. D. Product description.
18. Cost control outputs include all of the following except:
A. Estimate at completion.
B. Budget updates.
C. Revised cost estimates.
D. Cost baseline.
19. Risk identification outputs include the following except:
A. Decision trees.
B. Inputs to other processes.
C. Risk symptoms.
D. Potential risk events.
20. Puts into overall change control include all of the following except:
A. Project plan.
B. Change requests.
C. Change control system.
D. Performance reports
參考答案:
1.B 2.A 3.C 4.B 5.C 6.A 7.A 8.D 9.B.10.B 11.C 12.D 13.A 14.D 15.D 16.A 17.C 18.D 19.A 20.C
- 1二級建造師資格證書不予注冊的理由及需要補(bǔ)充的材料
- 22010年上半年建筑生產(chǎn)安全事故情況通報(bào)
- 3給水排水工程大學(xué)專業(yè)排名
- 4怎樣掌握天然花崗石的特性?
- 5河北省青縣土地開發(fā)整理示范項(xiàng)目規(guī)劃設(shè)計(jì)報(bào)告
- 6項(xiàng)目標(biāo)準(zhǔn)化管理手冊
- 7防雷設(shè)計(jì)中的接地問題
- 8一級建造師市政公用工程管理與實(shí)務(wù)復(fù)習(xí)要點(diǎn):混凝土路面
- 9青海5年內(nèi)對既有公建實(shí)施抗震加固
- 10一級建造師管理與實(shí)務(wù)復(fù)習(xí)要點(diǎn):非常規(guī)起重設(shè)備
- 11國務(wù)院:27項(xiàng)全國重大水利工程已開工22項(xiàng)
- 122015年二級注冊消防工程師考試《綜合能力》備考資料(9)
- 13一級建造師法規(guī)及相關(guān)知識復(fù)習(xí)要點(diǎn):代理
- 14該如何備考2008年注冊造價(jià)工程師執(zhí)業(yè)資格考試?
- 15PVC防水卷材屋面工程施工控制
- 16632項(xiàng)行政審批事項(xiàng)被取消和下放 下一步要注重管放結(jié)合
- 17某工程環(huán)境因素臺帳
- 18住房城鄉(xiāng)建設(shè)部、文化部、財(cái)政部要求加強(qiáng)傳統(tǒng)村落保護(hù)發(fā)展工作
- 19義烏市2015年度二級建造師考試報(bào)考條件
- 20幕墻工程施工工藝標(biāo)準(zhǔn)(新ZS-10-全套)
- 21建設(shè)工程項(xiàng)目管理:建設(shè)工程現(xiàn)場職業(yè)健康安全衛(wèi)生的要求
- 22吉林推進(jìn)建筑廢棄物綜合利用
- 23一級建造師復(fù)習(xí)資料:機(jī)電工程施工圖設(shè)計(jì)階段的管理要求
- 24鄭州新修馬路怎么說塌就塌了?
- 25一級建造師復(fù)習(xí)資料:施工單位應(yīng)當(dāng)承擔(dān)的消防施工質(zhì)量和安全責(zé)任
- 26鋼纖維混凝土隧道的耐久性能研究
- 272015年造價(jià)員考試《土建工程》知識點(diǎn):土石方工程施工
- 28全國“治違行動”號聲響起
- 294月房屋市政工程事故同比減少
- 302015年咨詢工程師《工程咨詢概論》第十章(5)
成都公司:成都市成華區(qū)建設(shè)南路160號1層9號
重慶公司:重慶市江北區(qū)紅旗河溝華創(chuàng)商務(wù)大廈18樓