當(dāng)前位置:工程項(xiàng)目OA系統(tǒng) > 建筑OA系統(tǒng) > 建筑工程項(xiàng)目管理軟件
PMP認(rèn)證考試試題精選(5)以及答案
A. Organizational Planning
B. Resource Planning
C. Team Development
D. Staff Acquisition
82.The primary conmunication skills you will use in working with members of your project team will be:
A. Problem solving
B. Negotiating
C. Team building
D. Public relations
83.The primary conmunication skills you will use in working with your project sponsor will be:
A. Problem solving
B. Negotiating
C. Team building
D. Public relations
84.The primary conmunication skills you will use in working with functional managers will be:
A. Problem solving
B. Negotiating
C. Team building
D. Public relations
85.The primary conmunication skills you will use in working with external stakeholders will be:
A. Problem solving
B. Negotiating
C. Team building
D. Public relations
86.According to A H. Maslow, people~ needs must be satisfied according to a certain hierarchy.The order in which needs must be satisfied is:
A. Self-actualization, esteem, social, safety, physiological
B. Physiological, seW-actualization, social, esteem, safety
C. Physiological, safety, social, esteem, self-actualization
D. Self-actualization, social, physiological, safety, esteem
87.According to C. P. Alderfer, people~ needs fall into three broad categories. Which of the following is not one of Alderfer抯 categories?
A. Existence needs
B. Identity needs
C. Relatedness needs
D. GroMh needs
88.Your project plan requires personnel to wear a Radiation Monitor counter at all times while they are within the protected area surrounding a nuclear reactor. This requirement arises from your concern for:
A. Quality assurance reporting requirenrnts
B. Personnel safety needs
C. Stakeholder reporting requirements
D. Personnel physiological needs
89.A staffing management plan includes all of the following except:
A. Determining how to bring team members onto the project
B. A resource histogram
C. Determining how to release team members from the project
D. Documentation on who has the authority to make decisions
- 110月23日成都建材行情預(yù)測:與昨日持平
- 2海寧市三舉措助推建筑節(jié)能工作
- 3門式剛架的一些基礎(chǔ)知識(shí)
- 4幕墻及鋼結(jié)構(gòu)制作安裝工程施工組織設(shè)計(jì) 39P
- 52015年一級建造師教材機(jī)電工程預(yù)習(xí):焊接技術(shù)
- 620m預(yù)制T梁全套設(shè)計(jì)圖紙
- 72015造價(jià)工程師安裝工程知識(shí)點(diǎn):電氣設(shè)備元件和材料使用程序
- 82015年二級建造師考試《施工管理》模擬試題(四)
- 92015年安全工程師《安全生產(chǎn)管理知識(shí)》每日一練(10.14)
- 10直埋電纜敷設(shè)應(yīng)避免在的地段有哪些?
- 112009年二級建造師考試《水利水電》考試專家解析(30)
- 122015二級建造師考試輔導(dǎo):《機(jī)電工程管理與實(shí)務(wù)》(4)
- 13某小區(qū)西區(qū)15 17 20#住宅樓工程雨季施工方案
- 14閽㈢瓔宸ョ▼鏂藉伐鏂規(guī)?
- 15項(xiàng)目管理知識(shí):項(xiàng)目采購管理4
- 16上海近自然型水景住宅建設(shè)
- 17造價(jià)工程師《技術(shù)與計(jì)量安裝》第四章工程施工技術(shù)(6)
- 18二級建造師基礎(chǔ)學(xué)習(xí)詞匯:距離測量的操作方法
- 19建筑工程落地外腳手架施工技術(shù)交底
- 20商品混凝土攪拌站基本特性
- 21綜合管理:中國IT產(chǎn)業(yè)項(xiàng)目管理之現(xiàn)狀
- 22一級建造師項(xiàng)目管理復(fù)習(xí)資料——合同實(shí)施的偏差分析
- 23材料取樣標(biāo)準(zhǔn)
- 242014一級建造師市政知識(shí)點(diǎn):索塔施工的技術(shù)要求和注意事項(xiàng)
- 25二級建造施工復(fù)習(xí)要點(diǎn):瓦工作業(yè)安全常識(shí)
- 262015二級建造師考試《建設(shè)工程施工管理》場景練習(xí)(二)
- 27一級建造師建設(shè)工程經(jīng)濟(jì)復(fù)習(xí)資料——價(jià)格總水平的含義和度量
- 282015年二級建造師考試《施工管理》重點(diǎn)講義(4)
- 292015造價(jià)工程師考試《基礎(chǔ)理論與相關(guān)法規(guī)》考點(diǎn)(44)
- 30中冶華天首次中標(biāo)城市餐廚垃圾處理咨詢項(xiàng)目
成都公司:成都市成華區(qū)建設(shè)南路160號1層9號
重慶公司:重慶市江北區(qū)紅旗河溝華創(chuàng)商務(wù)大廈18樓