PMP認證考試練習(xí)題及參考答案(三十六)
A Capital budgeting process.
B Overhead rates.
C Contracts and administration costing system.
D Fringe benefits packages.
E None of the above. www.Examda.CoM
ans:B
2 Management reserves are normally defined as a % of the total budget. As a project progresses, the project manager wants the $ value of management reserve to _____, whereas the customer wants the management reserve to _____.
A Increase, increase.
B Increase, decrease.
C Decrease, decrease.
D Decrease, increase.
E Remain the same, return to customer.
ans:E
3 The most effective means of determining the cost of a project is to price out the _____.
A Work breakdown structure.
B Linear responsibility chart. 來源:考試大
C Project charter.
D Scope statement.
E Management plan.
ans:A
4 The most expensive phase of life cycle costing is:
A R & D.
B Applied research.
C Production
D Operations and support.
E Termination.
ans:D
5 A _____ estimate prepared from layouts, sketches and flowsheets, should be accurate within (-10, +25%).
A Parametric
B Definitive.
C Budget
D Bottom up.
E Top down.
ans:C
6 The most precise or accurate estimate for determining project costs is the _____ estimate.
A Definitive.
B Analogy
C Budget
D Modified standards.
E Rule of thumb.
ans:A
7 Statistical cost estimating techniques (based upon history), are called _____ estimates and are a _____ approach.
A Definitive, bottom up.
B Analogy, top down.
C Parametric, bottom up.
D Parametric, top down. www.Examda.CoM
E Analogy, bottom up.
ans:D
8 A(n) _____ system is designed to ensure the timely availability of nonhuman resources, and includes the cost in procurement, shipping/freight, storage and loss.
A Inventory control.
B Materials management.
C Procurement.
D All of the above.
E A and C only.
ans:B
9 There are two major types of reserves used on projects. The _____ is for (usually major) scope changes that were not considered as part of the original plan, whereas the _____ is to compensate for minor changes in estimating, escalation factors.
A Management reserve, unplanned allowance fund.
B Management reserve, contingency.
C Contingency fund, management reserve.
D Unplanned allowance fund, budgetary reserve.
E Unplanned reserve, planned reserve.
ans:C
10 Project cash reserves are often used for adjustment in escalation factors which may be beyond the control of the project manager. Other than possibly financing (interest) costs and taxes, the three most common escalation factors involve changes in:
A Overhead rates, labor rates and material costs.
B Overhead rates, schedule slippages, and rework.
C Rework, cost-of-living adjustments, and overtime.
D Material costs, shipping cost, and scope changes.
E Labor rates, material costs, and cost reporting.
ans:A
11 The three most common types of project cost estimates are:
A Order of magnitude, parametric, and budget.
B Parametric, definitive and top down.
C Order of magnitude, definitive and bottom up.
D Order of magnitude, budget and definitive.
E Analogy, parametric and top down.
ans:D
12 The work breakdown structure, the work packages, and the company's accounting system are tied together through the:
A Code of accounts.
B Overhead rates.
C Budgeting system.
D Capital budgeting process.
E All of the above.
ans:A
- 1《宏觀經(jīng)濟政策與發(fā)展規(guī)劃》知識點:我國重點產(chǎn)業(yè)的確定
- 22015年招標師考試招標采購專業(yè)實務(wù)考前復(fù)習(xí)指導(dǎo)(91)
- 3合同洽談與溝通
- 42015年安全工程師安全生產(chǎn)管理知識模擬題(6)
- 5造價工程師造價案例分析復(fù)習(xí)要點:延尺系數(shù)
- 6城市熱力管道工程管道安裝及檢驗的施工要求
- 7湖南機械為您介紹混凝土輸送泵管道如何架設(shè)
- 8攪拌車底盤養(yǎng)護注意事項
- 9項目員工教育培養(yǎng) 內(nèi)容
- 103某工程園林工程技術(shù)標書
- 112015年一級建造師《工程經(jīng)濟》第一篇沖刺講義(1)
- 12安徽注冊消防工程師資格考試輔導(dǎo)教材征訂
- 13規(guī)范招標文件編寫(上)
- 14儲秀斌:貧困縣形象工程 見怪不怪
- 152013年內(nèi)蒙古二級建造師注冊證書、執(zhí)業(yè)印章遺失補辦申請表
- 16驚嚇!越南羽毛球公開賽現(xiàn)場 體育館房頂突然坍塌
- 172015年咨詢工程師《工程項目組織與管理》每日一練(1.11)
- 182015年安全工程師考試《管理知識》模擬題(39)
- 19[開封]07造價工程師考試6.11起報名
- 202015年招標師《項目管理與招標采購》練習(xí)及答案7
- 21造價工程師技術(shù)與計量復(fù)習(xí)要點:相應(yīng)腳手架
- 22某立交橋鋼箱梁液壓提升安裝施工
- 23安全工程師生產(chǎn)技術(shù)復(fù)習(xí)要點:傳送帶
- 24強夯法加固機理有哪些要求?
- 25工程造價基礎(chǔ):開標、評標與定標
- 26[廣州]大型工程施工進度計劃、資源需求計劃
- 272015年福州安全工程師報名時間
- 28中鐵電氣化局西格二線關(guān)角隧道首臺箱變一次送電成功
- 29交通運輸安全技術(shù)模擬試題及參考答案
- 302012一級建造師《公路工程》:中心站集中拌合法施工
成都公司:成都市成華區(qū)建設(shè)南路160號1層9號
重慶公司:重慶市江北區(qū)紅旗河溝華創(chuàng)商務(wù)大廈18樓