監(jiān)理公司管理系統(tǒng) | 工程企業(yè)管理系統(tǒng) | OA系統(tǒng) | ERP系統(tǒng) | 造價咨詢管理系統(tǒng) | 工程設(shè)計管理系統(tǒng) | 甲方項目管理系統(tǒng) | 簽約案例 | 客戶案例 | 在線試用
X 關(guān)閉
軟件項目管理工具

當(dāng)前位置:工程項目OA系統(tǒng) > 建筑OA系統(tǒng) > 軟件項目管理工具

PMP認證考試練習(xí)題及參考答案(二十四)

申請免費試用、咨詢電話:400-8352-114

1 Which of the following can be tracked using the WBS?
A time
B cost
C performance
D scope http://ks.examda.com
E None of the above.
ans:D
2 Which of the following are types of status reports?
A document, variance, trend and exception
B cost, trend, schedule and acquisition
C cost, schedule, technical performance
D analysis, cost, performance and schedule
E All of the above.
ans:C
3 You have been assigned as a project leader and must first review the statement of work provided by the customer. Which of the following is most often overlooked?
A Data item deliverables
B Customer-furnished equipment and facilities
C Long-lead procurement items
D Customer-imposed milestones
E Other subcontractor interface requirements
ans:A
4 During the planning phase of a project, you realize that more than one functional department possesses the skill and technical know-how to perform a given task. The best way for the project manager to handle this would be to:
A Make the decision, document it in the linear responsibility chart, and distribute the chart to all departments.
B Let the affected line groups decide among themselves who will perform the work
C Ask the executive sponsor to make the decision 來源:考試大網(wǎng)
D Allow each line group to perform part of the task
E All of the above
ans:B
5 The most common definition of project success is:
A Within time
B Within time and cost
C Within time, cost and technical performance requirements
D Within time, cost, performance and accepted by the customer/user
E None of the above
ans:D
6 The scope of a project can be expected to change if:
A The project manager must provide cost estimates without having a design concept
B Oversimplification (underestimating) of the nature of the work occurs
C The project manager is assigned after the project is defined, and the cost and schedule are approved
D A clear objective is not provided
E All of the above are possible based upon the situation
ans:E
7 The most common non-behavioral reason for projects being completed behind schedule and over budget is:
A Selecting the wrong person as the project manager
B Selecting the wrong person as the sponsor
C Accepting a high-risk project 考試大(www.Examda。com)
D Ill-defined requirements
E All of the above
ans:D
8 The appointment or selection of a project sponsor is often based upon:
A The strategic importance of the project
B Who the customer is
C Whether the organization is project or non-project-driven
D The profitability of the project
E All of the above
ans:E
9 The "rolling wave" or "moving window" concept is used most frequently on projects where:
A The baseline is frozen for the duration of the project and no scope changes are permitted
B Marketing is unsure of what the customer actually wants and reserves the right to make major scope changes
C The low levels of the work breakdown structure are known with certainty for the next three to six months, but the remaining tasks are based upon the results of the first three to six months of work
D Networking techniques are not appropriate
E All of the above
ans:C
10 Interfacing with the customer after project go-ahead is the responsibility of:
A Project sponsor
B Project team
C Project manager 來源:考
D Functional manager
E All of the above are possible, based upon the size and complexity of the project
ans:C
11 Using the WBS shown in the Special window, a typical work package would be:
A Software development
B Systems design
C Coding
D A, B, and C
E None of the above.
ans:E
12 Feasibility studies evaluate alternatives in terms of
A Cost-effectiveness
B Ease of performance
C Risk
D Safety
E All or part of A through D
ans:E
發(fā)布:2007-03-02 10:50    編輯:泛普軟件 · xiaona    [打印此頁]    [關(guān)閉]
相關(guān)文章:

泛普軟件項目管理工具其他應(yīng)用

項目管理工具 禪道項目管理軟件 夢龍項目管理軟件 微軟項目管理軟件 裝飾管理系統(tǒng) 裝修預(yù)算軟件 項目計劃軟件 項目進度管理軟件 軟件項目管理工具 材料管理軟件 工程項目管理軟件系統(tǒng) 項目管理系統(tǒng) 施工管理軟件 建筑工程項目管理軟件 工程管理軟件