QUEST A deficiency in characteristics that render the quality of the material/service unacceptable is usually referred to as: 
A defective 
B defect 
C non-conformance 
D poor workmanship 
E lack of fitness for use 
參考答案:C

QUEST The formal invitation to submit a price for specified goods/services is usually referred to as: 
A request for proposal 
B request for quotation 
C tender invitation 
D bid invitation 
E A and B only 
參考答案:B

QUEST Which of the following is not part of contract administration 
A contract award 
B performance control 
C financial control 
D contract closeout 
E All of the above are parts of contract administration. 
參考答案:A

QUEST Which of the following is not part of the acquisition process: 
A source selection 
B invitation to bid 
C contract award 
D notice to proceed 
E All of the above are parts of the acquisition process. 
參考答案:D

QUEST Management reserve is generally intended to be used to: 
A implement additional unbudgeted scope 
B compensate for inaccurate estimates 
C cover major unforeseen catastrophes 
D cover unforeseen problems in the project 
E All of the above. 
參考答案:D

相關試題:

2010年PMP美國項目管理考試習題及答案33

試題推薦:

2010年PMP美國項目管理認定考試全真模擬試題精選1

2010年PMP美國項目管理認定考試全真模擬試題精選2

2010年PMP美國項目管理認定考試全真模擬試題精選3

發(fā)布:2007-03-02 10:53    編輯:泛普軟件 · xiaona    [打印此頁]    [關閉]
相關文章:

泛普軟件項目管理工具其他應用

項目管理工具 禪道項目管理軟件 夢龍項目管理軟件 微軟項目管理軟件 裝飾管理系統(tǒng) 裝修預算軟件 項目計劃軟件 項目進度管理軟件 軟件項目管理工具 材料管理軟件 工程項目管理軟件系統(tǒng) 項目管理系統(tǒng) 施工管理軟件 建筑工程項目管理軟件 工程管理軟件