2010年P(guān)MP美國項(xiàng)目管理考試習(xí)題及答案三十八

申請免費(fèi)試用、咨詢電話:400-8352-114

QUEST Time management is the allocation of time in a project's life cycle through the process of: 
A Planning 
B Estimating. 
C Scheduling. 
D Controlling 
E All of the above. 
參考答案:E

QUEST Using the situation shown in the Special window and assuming continues efficiency for work-in-progress and fixed price contract for task four.  The estimate at completion is: 
A $19K 
B $21K 
C $26K 
D $29K 
E indeterminate 
參考答案:C

QUEST Using the situation stated in the Special window,   a comparison of the cost variance of August as compared to July shows that the magnitude ($ value) of the variance has _____ and the percentage change has _____. 
A Become worse, become worse 
B Become worse, improved 
C Improved, increased 
D Improved, become worse 
E None of the above are correct 
參考答案:B

QUEST The computation for Cost Performance Index is: 
A BCWP/ACWP 
B BCWP-ACWP 
C BCWP-BCWS 
D ACWP/BCWP 
E ACWP-BCWS 
參考答案:A

QUEST When comparing the cost of competing projects, which of the following is typically NOT considered? 
A Opportunity costs. 
B Direct costs. 
C Sunk costs. 
D Indirect costs. 
E Burden rates. 
參考答案:C

相關(guān)試題:

2010年P(guān)MP美國項(xiàng)目管理考試習(xí)題及答案三十七

試題推薦:

2010年P(guān)MP美國項(xiàng)目管理認(rèn)定考試全真模擬試題精選1

2010年P(guān)MP美國項(xiàng)目管理認(rèn)定考試全真模擬試題精選2

2010年P(guān)MP美國項(xiàng)目管理認(rèn)定考試全真模擬試題精選3

發(fā)布:2007-03-02 10:54    編輯:泛普軟件 · xiaona    [打印此頁]    [關(guān)閉]
相關(guān)文章:

泛普軟件項(xiàng)目管理工具其他應(yīng)用

項(xiàng)目管理工具 禪道項(xiàng)目管理軟件 夢龍項(xiàng)目管理軟件 微軟項(xiàng)目管理軟件 裝飾管理系統(tǒng) 裝修預(yù)算軟件 項(xiàng)目計(jì)劃軟件 項(xiàng)目進(jìn)度管理軟件 軟件項(xiàng)目管理工具 材料管理軟件 工程項(xiàng)目管理軟件系統(tǒng) 項(xiàng)目管理系統(tǒng) 施工管理軟件 建筑工程項(xiàng)目管理軟件 工程管理軟件