QUEST Using the figure in the Special window,  Activity "L" has an early start time of _____ weeks and an early finish time of _____ weeks. 
A 11, 13 
B 12, 14 
C 13, 15 
D 14, 16 
E 15, 17 
參考答案:E

QUEST Using the figure in the Special window,  The Critical path is _____ weeks. 
A 21 
B 22 
C 23 
D 24 
E 25 
參考答案:D

QUEST Using the data shown in the Special window,  Activities P, Q, and T are critical path activities.  In order to shorten the time duration of the project, which activity should be "crashed" first? 
A P 
B Q 
C R 
D S 
E T 
參考答案:A

QUEST Using the figure in the Special window,  By how many weeks can activity "F" slip without extending the end date of the project? 
A 0 
B 1 
C 2 
D 3 
E 4 
參考答案:D

QUEST Using the figure in the Special window,  The critical path is: 
A A-B-G 
B C-G 
C C-D 
D E-F 
E A-B-G and C-D 
參考答案:B

相關試題:

2010年PMP美國項目管理考試習題及答案二十八

試題推薦:

2010年PMP美國項目管理認定考試全真模擬試題精選1

2010年PMP美國項目管理認定考試全真模擬試題精選2

2010年PMP美國項目管理認定考試全真模擬試題精選3

發(fā)布:2007-03-02 10:55    編輯:泛普軟件 · xiaona    [打印此頁]    [關閉]
相關文章:

泛普軟件項目管理工具其他應用

項目管理工具 禪道項目管理軟件 夢龍項目管理軟件 微軟項目管理軟件 裝飾管理系統(tǒng) 裝修預算軟件 項目計劃軟件 項目進度管理軟件 軟件項目管理工具 材料管理軟件 工程項目管理軟件系統(tǒng) 項目管理系統(tǒng) 施工管理軟件 建筑工程項目管理軟件 工程管理軟件