PMP美國項(xiàng)目管理認(rèn)證的模擬考試的樣題9
申請(qǐng)免費(fèi)試用、咨詢電話:400-8352-114
1. Management decision-making includes:A. Analysis of alternatives.
B. Revisions/replanning.
C. Resource allocation.
D. Modification or updating of goals and objectives.
E. All of the above.
ANS: E
2. The basic terminology for networks includes:
A. Activities, events, manpower, skill levels and slack.
B. Activities, documentation, events, manpower and skill
levels.
C. Slack, activities, events, and time estimates.
D. Time estimates, slack, sponsorship involvement, and
activities.
E. Time estimates, slack time, report writing, life
cycle phases, and crashing times.
ANS: C
3. The project manager must receive reports and
briefings from engineers, contracting officers,
procurement personnel and marketing people.
The project manager’s communication dilemma is one of:
A. encoding
B. decoding
C. choice of a medium
D. one-way communication
E. All of the above.
ANS: E
4. The technique most commonly used to determine the
profitability of a project includes _____ methods.
A. Net present value (NPV).
B. Return on investment (ROI).
C. Discounted cash flow (DCF)
D. Payout time and risk sensitivity analysis.
E. All of the above.
ANS: E
5. Which of the following are part of the purchasing
cycle:
A. define need
B. prepare and issue purchase order
C. inspect incoming goods
D. All of the above.
E. A and B only
ANS: E
6. Which of the following is closest to Juran’s
definition of Quality:
A. conformance to requirements.
B. fitness for use.
C. continuous improvement.
D. customer focus.
E. All of the above.
ANS: B
7. A project element which lies between two events is
called:
A. An activity.
B. A critical path method.
C. A slack milestone.
D. A timing slot.
E. A calendar completion point.
ANS: A
8. Employee unions would most likely satisfy which
level in Maslow’s hierarchy of needs?
A. Belonging
B. Self-actualization
C. Esteem
D. Safety
E. Empowerment
ANS: A
9. Management calls a meeting to explain to all
employees the new benefits package for the rank and
file. This is an example of:
A. Upward communication
B. Downward communication
C. One-way communication
D. Two-way communication
E. None of the above.
ANS: C
10. Project management/project planning is most closely
aligned with:
A. Long range/strategic planning (5 years or more).
B. Intermediate range planning (1 to 5 years)
C. Short range/tactical planning (1 year or less).
D. All of the above.
E. B and C.
ANS: E
- 12015招標(biāo)師《項(xiàng)目管理與招標(biāo)采購》:履行合同的擔(dān)保形式
- 2安全生產(chǎn)事故案例分析:案例4及練習(xí)
- 32015年監(jiān)理工程師考試合同管理練習(xí)題(49)
- 4苗木養(yǎng)護(hù)工程施工組織設(shè)計(jì)
- 5景觀工程施工組織設(shè)計(jì)30p
- 6一級(jí)建造師工程經(jīng)濟(jì)復(fù)習(xí)要點(diǎn):存貨總成本
- 7海南8個(gè)重點(diǎn)公路建設(shè)項(xiàng)目 總投資約280億
- 8安全工程師《安全生產(chǎn)管理》第四講講義精選(4)
- 92015年招標(biāo)師法律法規(guī)高頻考點(diǎn):投標(biāo)保證金的提交
- 10天津2015年的招標(biāo)師考試培訓(xùn)
- 112015年咨詢工程師《工程項(xiàng)目組織與管理》每日一練9.3
- 12PMP認(rèn)證考試練習(xí)題及參考答案(三十八)
- 13聞異常氣味判斷混凝土攪拌車故障
- 14造價(jià)工程師復(fù)習(xí)資料:融資談判階段的主要工作
- 15《項(xiàng)目決策分析與評(píng)價(jià)》知識(shí)點(diǎn):項(xiàng)目目標(biāo)
- 162015年一級(jí)建造師考試《法規(guī)及相關(guān)知識(shí)》沖刺習(xí)題(16)
- 17工程檔案不需移交城建檔案管理部門,暫由建設(shè)單位保管的有
- 18混凝土泵的工作方式
- 192008年監(jiān)理工程師《質(zhì)量、投資、進(jìn)度控制》習(xí)題26
- 20鋼筋出廠質(zhì)量合格證的驗(yàn)收內(nèi)容是什么
- 21項(xiàng)目管理與招標(biāo)采購第三章:特種設(shè)備管理的范圍
- 2209年注冊(cè)安全工程師事故案例分析模擬試題(四十一)
- 23一級(jí)建造師管理與實(shí)務(wù)復(fù)習(xí)要點(diǎn):減水劑
- 24某市政雨水管道工程施工組織設(shè)計(jì)
- 252015年咨詢工程師《工程項(xiàng)目組織與管理》每日一練4.21
- 26淮南市多措并舉推動(dòng)美好鄉(xiāng)村建設(shè)產(chǎn)業(yè)發(fā)展
- 27招標(biāo)師考試《招標(biāo)采購案例分析》資料(6)
- 28“十二五”我國將易地扶貧搬遷240萬人
- 292015年咨詢工程師《工程項(xiàng)目組織與管理》每日一練12.23
- 30【招標(biāo)師考試】項(xiàng)目管理與招標(biāo)采購第五章(匯總)
成都公司:成都市成華區(qū)建設(shè)南路160號(hào)1層9號(hào)
重慶公司:重慶市江北區(qū)紅旗河溝華創(chuàng)商務(wù)大廈18樓