PMP認證考試練習題及參考答案(九)
1. financial compensation is the primary motivational tool for which of the following management theories of programs.
a. zero-defects program.
b. theory x management.
c. theory y management.
d. quality control circles.www.Examda.CoM
e. a and c
ans: b
2. in which of the following contract types is it easier to change the scope of the contract:
a. firm fixed price
b. fixed price plus incentive fee
c. cost plus percentage of cost
d. letter contract
e. none of the above.
ans: c
3. planning activities such that predetermined resource availability pools are not exceeded is called:
a. resource leveling.
b. manpower leveling.
c. resource limited planning.
d. manpower planning.
e. manpower contingency planning.
ans: c
4. the project charter:考試大論壇
a. expresses upper management commitment to the project.
b. provides that authority by which the project will be run.
c. establishes that organizational structure with the project.
d. specifies overall objectives and timeframe of the project.
e. all of the above.
ans: e
5. which of the following areas are addressed in risk identification:
a. environmental
b. technical
c. legal
d. all of the above.
e. a and b only
ans: d
6. which of the following types of power comes through the organizational hierarchy
a. coercive
b. reward
c. referent
d. legitimate
e. experthttp://ks.examda.com
ans: d
7. a calendar that identifies when a project may be performed on an activity is called a:
a. project calendar.
b. resource calendar.
c. milestone point.
d. key point.
e. work unit.
ans: a
8. charisma would be an example of _____ power.
a. legitimate
b. reward
c. coercive
d. expert
e. referent
ans: e
9. for every situation, several methods usually exist for effective communication to take place. which of the following is least likely to be used
for explaining to the team project planning guidelines?
a. project office memo
b. project office directive
c. project team meeting
d. formal reportwww.Examda.CoM
e. counseling sessions
ans: d
10. in the project environment, the individual ultimately responsible for quality control is:
a. the line workers who must strive "to do things right the first time" to avoid quality problems.
b. the company's quality control manager who must work with the project members to ensure the quality control program is effective.
c. the head of the production department who retains ultimate quality control responsibility for all the company's projects.
d. the project manager who has ultimate responsibility for the entire project.
e. the customer who must ensure that he is receiving a quality product from the vendor.
ans: d
11. in which of the following types of contracts is it most important for the contractor to maintain control of cost, schedule and scope changes.
a. unit price
b. cost plus incentive fee
c. cost plus fixed fee
d. firm fixed price
e. b and d only
ans: d
12. middle (functional) managers have the greatest influence in the direction of the project in which type of organizational structure?
a. project.
b. strong matrix.
c. weak matrix.
d. project coordinator.
e. project expeditor.
ans: c
- 12015一級建造師《市政工程》講義摘要(15)
- 2工程咨詢概論:政府投資補助
- 3消防工程師考試難度怎么樣
- 4安全工程師輔導資料:電力施工安全管理5
- 5廣州某學院綜合樓施工臨時用電平面布置圖
- 6二級建造師注冊流程
- 7一級建造師法規(guī)及相關知識復習要點:代位權的行使
- 8混凝土實心板有鋼筋嗎
- 9廣西2015年注冊安全工程師執(zhí)業(yè)資格考試考務工作通知
- 10建筑外墻防水施工工藝(2011年 多圖)
- 11天津今年同期建5條地鐵線 2號線8月底全線貫通
- 122015年招標師考試招標采購專業(yè)實務考前復習指導(102)
- 132015年造價工程師考試輔導:Partnering模式
- 14某村鎮(zhèn)給水管道工程施工組織設計
- 152015年造價工程師考試《理論與法規(guī)》知識點總結(3)
- 16安全工程師答疑精華:過罰相當原則
- 172015年造價工程師考試《計價控制》第二章講義(3)
- 18安全工程師《法律法規(guī)》習題班講義精選(96)
- 19安全工程師生產法復習資料——簽訂委托評價合同
- 20造價工程師技術與計量(土建)復習資料——汽車起重機
- 212015年咨詢工程師《現(xiàn)代咨詢方法與實務》練習題(22)
- 222015年招標師考試招標采購專業(yè)實務考前復習指導(58)
- 232015年咨詢工程師《宏觀經濟政策與發(fā)展規(guī)劃》每日一練(6.28)
- 242015招標師考試教材重點:合同法的基本原則
- 252015年咨詢工程師《工程咨詢概論》模擬題(18)
- 26軟件項目管理如何加強土建施工現(xiàn)場管理的重要性?
- 272015年招標師:招標采購專業(yè)實務精選習題49
- 28工程造價的審核方法和審核內容有哪些
- 29建筑防水工程技術探討
- 30某濕陷性黃土地區(qū)明挖隧道(投標)施工組織設計
成都公司:成都市成華區(qū)建設南路160號1層9號
重慶公司:重慶市江北區(qū)紅旗河溝華創(chuàng)商務大廈18樓