QUEST Risk mitigation involves all but which of the following:
A developing system standards (policies, procedure, responsibility standards)
B obtaining insurance against loss
C identification of project risks
D performing contingent planning
E developing planning alternatives
參考答案:C
QUEST The principles of risk management should be followed only for:
A complex projects
B simple projects
C large projects
D A and C
E All of the above.
參考答案:E
QUEST The type of contract (payment mechanism) chosen for a project is often a reflection of the degree of risk associated with completing that project. For a firm fixed price contract, payment for risk _____ .
A Is accomplished by paying the actual costs to the contractor.
B Is accomplished by paying the contractor for his costs plus a fixed fee (profit).
C Is an undisclosed contingency in the contractor's bid.
D Is accomplished by paying for the budgeted costs of dealing with risks, as predicted in the project risk assessment.
E B and C
參考答案:C
QUEST Risk can be divided into two basic types; business risk and pure (or insurable risk). Of the following, which one(s) fall(s) under business risk?
A liability loss
B direct property loss
C profit loss
D personnel-related loss
E B and C
參考答案:C
QUEST Risk classified as unknown unknowns (i.e., those which cannot be identified or evaluated):
A should be deflected to the contracting officer
B should be handled via contingency allowances
C should be ignored, since they cannot be identified
D should be ignored, since they are not covered in the Project Risk Assessment
E C and D
參考答案:B
相關(guān)試題:
2010年P(guān)MP美國項目管理考試習題及答案17
試題推薦:
2010年P(guān)MP美國項目管理認定考試全真模擬試題精選1
2010年P(guān)MP美國項目管理認定考試全真模擬試題精選2
2010年P(guān)MP美國項目管理認定考試全真模擬試題精選3
- 12015年監(jiān)理工程師考試《合同管理》習題(12)
- 22015年招標師《專業(yè)實務(wù)》輔導(dǎo):整個招標過程的時長
- 3怎樣才能保證錨桿具有較高的初錨力?
- 4上海市某路隧道工程施工組織設(shè)計
- 52015年招標采購專業(yè)實務(wù)輔導(dǎo):招標方案內(nèi)容3
- 6園林景觀設(shè)計的程序
- 72015年招標師考試每日一練(8月25日)
- 82015年海南省造價工程師報考需提供的材料
- 92015安全工程師《生產(chǎn)管理知識》試題精選(20)
- 10EPS板薄摸灰外墻外保溫施工工藝
- 11CIO如何管理大型信息工程項目
- 12《政策與發(fā)展規(guī)劃》知識點:中國農(nóng)業(yè)發(fā)展銀行
- 132015年長沙安全工程師報名時間
- 142015年咨詢工程師《咨詢概論》答疑:框架合同
- 15二級建造師考試復(fù)習總結(jié):加固工程的類型與功能
- 162015年咨詢工程師《項目決策分析與評價》每日一練(3.29)
- 17西安至銅川建城際鐵路 投資58億全長83公里
- 18山西:陵川中小學(xué)校舍危房改造全覆蓋
- 19美國項目管理PMP認證模擬考試試題精選4
- 20一級建造師管理與實務(wù)復(fù)習要點:質(zhì)量和安全事故
- 212015造價工程師《理論與法規(guī)》課程講座(9)
- 22二建復(fù)習資料施工合同的法律特征
- 232015年咨詢工程師《工程咨詢概論》每日一練9.26
- 242015年監(jiān)理工程師《建設(shè)工程三大控制》考試試卷
- 25某工程水暖系統(tǒng)施工組織設(shè)計 64p
- 262015造價員《土建工程》造價基礎(chǔ)知識:砌筑工程施工
- 27深基坑施工事故發(fā)生率高
- 28招標采購法律法規(guī)與政策大綱變動及對比情況
- 29施工公司違紀界定 內(nèi)容
- 302015年海南省安全工程師報名時間為6月1日~6月30日
成都公司:成都市成華區(qū)建設(shè)南路160號1層9號
重慶公司:重慶市江北區(qū)紅旗河溝華創(chuàng)商務(wù)大廈18樓